Abu Dhabi / WAM
The first of five turbines for the Hywind Scotland commercial-scale floating offshore wind farm has now sailed away from Stord in Norway to its final destination, Buchan Deep, 25 km east of
Peterhead in Scotland.
Masdar, Abu Dhabi’s renewable energy company, announced that it had acquired a 25% stake in the Hywind Scotland project during Abu Dhabi Sustainability Week in January.
All five turbines were successfully assembled outside Stord, Norway this summer. Now they are being individually towed to Scottish waters. Each turbine journey takes 4 days of sailing across the North Sea. On arrival, work immediately starts to install anchor lines and to perform hook-up operations, taking 2-3 days per turbine. Turbine installation is scheduled to be finished by the end of August.
In parallel, the loadout of the cables will commence in Halden, Norway. An installation vessel will then go to Kristiansand, Norway, to pick up vertical anchors and buoyancy modules before heading to Peterhead for pull-in of the export cable.