MANILA / Reuters
Australia-listed Energy World Corp expects to start up a gas-fired power plant in the Philippines by end-2018, its chief executive said, fed by the country’s first liquefied natural gas (LNG) imports.
The Philippines does not currently import LNG, but its domestic natural gas reserves are depleting, and the country has been developing plans for import terminals for years. EWC’s terminal on Pagbilao island in Quezon province, if started up this year, would mark the country’s first LNG imports.
“By the end of this year, we should have 400 megawatts (MW) in operation,†Energy World Corp (EWC) Managing Director and CEO Stewart Elliott told Reuters in an interview in Manila.
The generating capacity is part of a 650 MW power plant EWC is building in Quezon, located near its LNG receiving plant that is 90 percent complete, and will be capable of receiving 3 million tonnes of LNG a year, Elliott said. The company will initially source the gas from the spot market and later possibly from its Sengkang gas field in Indonesia, Elliot said.
EWC has been developing the power plant and import terminal since 2011 but completion has been set back by several delays.
Elliott said the project was now far enough advanced for EWC to have a tanker on stand-by in Singapore to bring in LNG once the facility is ready.